September 2025 update

Many rooftop solar arrays need no consent

People installing roof-mounted solar arrays up to 40m² will not need building consent where structural fixings and specified wind limits apply; the building code still applies.

Building (Exempt Roof-mounted Solar Panel Arrays and Building Work) Order 2025 · Starts 23 Oct 2025

What's changing

Building consent exemptions

From 23 October 2025, the order will change Schedule 1 of the Building Act 2004, which lists building work that does not need a building consent. The supplied text does not give the new setback distances or the detailed solar-panel conditions.

Who's affected

People carrying out exempt building work, including some owners of small detached buildings and roof-mounted solar panel arrays.

When

The order comes into force on 23 October 2025.

Background

The order changes the categories of building work that can be done without a building consent.

Read the official text on legislation.govt.nz