Biosolid users get clearer land rules

Wastewater treatment operators must tell biosolid users how land-discharge rules work, including new permitted limits of up to 300 kilograms per hectare yearly.

Water Services (Wastewater Environmental Performance Standards) Amendment Regulations 2026 · Starts 14 Aug 2026

What's changing

Biosolid information for end users

Wastewater treatment plant operators must take all reasonably practicable steps to tell biosolid end users the conditions for permitted land discharge and how to find more information.

Permitted biosolid application amounts

A biosolid discharge of no more than 300 kilograms per hectare each year will meet the specified permitted-activity conditions. Discharges above 300 and up to 1,000 kilograms will also need to meet additional conditions.

Overflow mapping and risk assessments

Resource consents for specified wastewater network activities will require operators to keep an up-to-date map of engineered and uncontrolled overflow points, and assess each new uncontrolled overflow point.

Coverage of wastewater rules

The rules will distinguish reticulated wastewater networks from treatment plants and exclude on-site systems discharging less than 20 cubic metres daily and serving no more than five homes.

Who's affected

Wastewater treatment plant operators, biosolid end users, wastewater network operators, consent holders, and consent authorities are affected.

When

These regulations are stated to take effect on 14 August 2026, while some provisions start on 1 September 2026 and regulation 8 starts on 19 December 2028.

What you might need to do

Background

The government says the regulations correct and clarify the 2025 wastewater standards and make other minor amendments.

Read the official text on legislation.govt.nz